Net metering is the legal right of Philippine solar owners to sell excess electricity back to their distribution utility (Meralco, VECO, etc.) at the prevailing generation rate. It is governed by Republic Act 9513 (Renewable Energy Act) and DOE Circular DC2013-05-0009. Here is the exact process.
| Step | Action | Timeline |
|---|---|---|
| 1 | Install solar system — get as-built drawings and permits from contractor | Before application |
| 2 | Download Meralco Net Metering Application Form from meralco.com.ph | Day 1 |
| 3 | Compile documents: single-line diagram, building permit, electrical permit, PRC-licensed EE signature | Day 1-5 |
| 4 | Submit application at Meralco Business Center (bring originals + photocopies) | Day 5-7 |
| 5 | Meralco inspection of installation | Within 30 days |
| 6 | Bidirectional meter installation by Meralco | Within 60 days |
| 7 | Sign Net Metering Agreement — valid for 10 years, renewable | After meter install |
Meralco credits excess generation at the blended generation charge — approximately ₱5.00-6.50/kWh (varies quarterly). This credit offsets your monthly bill. Unused credits roll over monthly but are forfeited annually (bank resets every March billing cycle).
Connect with DOE-accredited installers who handle the full net metering application for you at solarenergyph.shop.
Engr. Jason Morales — Founder, SolarEnergyPH