A grid-tied solar system must meet Meralco's Distribution Services and Open Access Rules (DSOAR) and the DOE's interconnection standards before it can legally operate. Non-compliant systems face disconnection and possible fines. Here is what compliance requires.
| Step | Document/Action Required | Timeline |
|---|---|---|
| 1 | Pre-application inquiry — submit system specs to Meralco | Before installation |
| 2 | Single-line diagram (signed by PRC EE) | With application |
| 3 | Inverter compliance certificate (IEEE 1547) | With application |
| 4 | Building/electrical permit from LGU | With application |
| 5 | Meralco technical inspection | Within 30 days of submission |
| 6 | Bidirectional meter installation | Within 60 days of approval |
| 7 | Commissioning and net metering agreement signing | After meter installation |
For VECO (Cebu), DLPC (Davao), or rural co-ops — the same DOE framework applies but local DU requirements vary. Always coordinate with your local distribution utility before installation, not after.